Case Study
SCA Obbola
New Recycled Fiber Line in an Operational Environment
In one of our most intensive and technically challenging assignments, WP Welding was a key partner to SCA in the Expansion Obbola project – a major industrial project outside Umeå. The goal was to build a new recycled fiber line to double the production capacity of recycled paper for SCA’s new paper machine.
We joined the project’s final phase in November 2022 and had up to 80 personnel from various disciplines on site during the execution. The work was carried out in an existing facility, simultaneously with parts of the factory still in operation – demanding high levels of planning, safety, and flexibility.
Our assignment included
Installation in an active production environment
Pipe and steel work
Coordination between multiple technical disciplines
Thanks to close collaboration with SCA, we delivered our part of the project on schedule — with high quality and excellent results.
“We are impressed by how solution-oriented WP Welding is and their ability to staff up with skilled personnel on short notice. They contributed greatly to making this intensive project run smoothly and successfully.“
– Oskar Persson, Installation Manager, SCA Obbola.
A contribution we are proud to have been part of.

Contact
Complex projects require the right competence from the start. We help you move forward with structure, experience, and clear deliveries.
Contact
John-John Choukair
Founder
john-john@wpwelding.se
0709 90 09 25
Oskar Hoflund
CEO
oskar.hoflund@wpelding.se
0722 19 05 63
Johan Wikemark
Project & Business Development
johan.wikemark@wpwelding.se
Office
Lysekil · Gothenburg · Luleå